25032008

Building B: 1FL Column Props Assembly

Building B: 1FL Column Props Assembly & Dismantle of Stair No.4 Wall Formwork

Building B: 1FL Column Props Assembly

Building B: 1FL Column Props Assembly


Building B: 1FL Column Props Assembly

Building A: 1FL Column Props Assembly


Building A: 1FL Column Props Assembly


Building A: 1FL Column Props Assembly
Date: 25 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health care City, UAE

22032008

Building B: 1FL Columns Concrete Pouring
Building B: 1FL Columns Concrete Pouring

Building A: 1FL Beam Props & Bottom Formwork Assembly

Building B: 1FL Service Inner Formwork Assembly & Rebars Erection

Building B: 1FL Stair No.4 Inner Formwork Assembly & Rebars Erection

Building B: 1FL Passenger Lift Inner Formwork Assembly & Rebars Erection


Building A: 1FL Beam Props & Bottom Formwork Assembly

Building B: 1FL Slab around GL.H~J/5~6 Concrete Pouring

Building B: 1FL Slab around GL.H~J/5~6 Concrete Pouring

Building B: 1FL Column Concrete Pouring

Date: 22 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health care City, UAE

18032008

Building B: 1FL Stair No.4 Rebars Erection

Building B: 1FL Column Formwork Assembly


Building B: 1FL Stair No.2 Rebars Erection


Building B: 1FL Column Formwork Assembly


Building A: 1FL Stair No.1 Rebars Erection and Wall Formwork Assembly


Building A: 1FL Lift Wall Rebars Erection

Building A: Stair No.1 Rebars Erection

Date: 18 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health Care City, UAE

12032008

Building B: 1FL Concrete Pouring

Building B: 1FL Concrete Pouring

Building B: 1FL Concrete Pouring

Building B: 1FL Concrete Pouring

Date: 12 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health Care City, UAE

10032008

Building A: Lift Wall Rebars Erection

Building A: 1FL Column Rebars Connection

Building A: 1FL Stair No.2 Wall Rebars Erection

Building B: 1FL Lift Wall Rebars Erection

Date: 10 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health Care City, UAE

08032008

Building B: 1FL Tendon, Rebars and Conduits Installation

Building B: 1FL Tendon, Rebars and Conduits Installation


Building B: 1FL Tendon, Rebars and Conduits Installation



Building B: 1FL Tendon, Rebars and Conduits Installation



B2FL: Block Work Installation

B2F: Block Work Installation

Date: 8 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health Care City, UAE

05032008

Building A: 1FL Slab Cast


Building A: 1FL Slab Cast



Building A: 1FL Concrete Pouring



Building A: 1FL Concrete Pouring


Building A: 1FL Conducts Installation





Date: 5 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health Care City, UAE

02032008

Building B: Installation of Construction Joint at 1FL GL.H~K/4~6

Building B: Installation of Construction Joint at 1FL GL.H~K/4~6


Building B: 1FL Tendon, Rebars and Conduits Installation



Building B: 1FL Tendon, Rebars and Conduits Installation


Building B: 1FL Tendon, Rebars and Conduits Installation


Building B: 1FL Tendon, Rebars and Conduits Installation



Building B: 1FL Tendon, Rebars and Conduits Installation



Date: 2 March 2008
Location: Urology, Nephrology, Diabetes & Diagnostic Imaging Hospital Project, Dubai Health Care City, UAE