04102007

Row 8: Rebars Erection

Lift Shaft No.3 & No.4

Lift Shaft No.5

Stair No.5 (Far)
Area A Status
Formwork Assembly for Ground Floor Slab on GL.D~H/3~7


Concrete Pouring for Stair No.1


Concrete Pouring for Stair No.1


Concrete Pouring for Row 8 Retaining Wall


Date: 04 October 2007
Location: Urology, Nephrology, Diebetes & Diagnostic Imaging Hospital Dubai Healthcare City, UAE